Basement Walls


Today the walls of the basement were trenched and poured.  The trencher digs a 9" wide trench, 11' 6" deep.  Rebar was added to the walls and corners.  I was amazed at the amount of concrete used.  Thirty yards in the walls alone.  The walls will dry 5-6 days then the dirt removed so the floor can be poured.  Hollye, Cade and Lanny came to watch the excitement.  
More later, Gary


 






Wednesday, May 13, 2009

Finally

After weeks and weeks of planning and waiting we are finally starting our house. We moved dirt to level the lot. Because of the soil we drilled piers 15' deep to rest the footing on. This house should not move or crack! The footing was dug today and hopfully the concrete poured tomorrow.Add Image


Thursday, May 7, 2009

New to us!

       Heather has me started in the blog world.  I will try to keep this current and up to date.
Gary